We should know the useful vb script function to manipulate strings. In this post, we will discuss some of the vb script function to manipulate strings and how they can be used in codes:

1. Instr searches for a string within another another string and returns the location of occurrence of one string within another string.It returns the position of first occurrence of the string.This function is used if we need to verify if a particular text appears in a string.


Syntax : InStr([start,]string1,string2[,compare])


Example - Report and loop in case a particular text in not found in the string :

If (Instr(1, string1, string2)>0) Then
    Reporter.ReportEvent micpass , "string 2 is found in string 1","As expected"
Else
    Reporter.ReportEvent micfail , "string 2 is  found in string 1","string 2 is not found in string1"
End If

2. InstrRev is similar to instr and can be used for similar purposes, with only difference search starts from the end of string, although count returned is from start of string.


InStrRev(string1,string2[,start[,compare]])


3. Trim , lTrim, Rtrim removes characters from both left and right, only left and only right respectively blank spaces.


4. Left , Right, and Mid returns a specified character from left, right, and middle of the string. 


Mid(string,start[,length])

5. len returns number of characters in the string.


6. Split splits a string based on the delimiter in the function.


Example - How to find the total number of occurrence of a string in another string.By default, string2 has value space if not provided.

arrString = split(string1,string2)
totOccurence = ubound(arrString)

Example- Total number of words in a string.

arrString = split(string1)
totOccurence = ubound(arrString)




What are different activities in Testing Process

Testing Process includes following activities that should be followed sincerely for proper testing.



1. Test Planning


Before beginning with testing, we need to define test plan based on which we perform testing for the rest of testing life cycle. We should develop a test plan based on following key points to be considered in testing life cycle.

  • Test Objectives should be measurable, prioritized, and should be signed off between stakeholders before moving forward with test planning. Acceptance Criteria should also be defined during objective settings to validate if the test objective has been accompanied.
  • Test Matrix should be defined on how to test the test objectives and to validate all the requirements are covered in testing.
  • Test Schedule should be defined, how milestones in testing will be covered and timeframe in which milestones will be delivered
  • Budgeting and resources planing should be defined.
  • Testing material including environment ans software/availability should be defined.
  • Training required for testing should be defined.


2. Test Control Activities

Once Test plan is created and signed off by stakeholder, Activities in test plan should be compared with actual and any deviation from the projected plan should be reported to stakeholders as risk.


3. Test Analysis

In this phase, test objectives defined in test planning are converted into test scenarios and test cases.Below are the main task in this phase:

  • Reviewing the test artifacts like business requirements, design, and test objectives.
  • Identifying and prioritizing test scenarios and test cases based on business requirements.
  • Identification of test data for execution of test conditions
  • Test environment availability


4. Test implementation

Below are activities in test implementation

  • Developing and prioritizing test cases with test steps
  • Preparation of test data for execution of test scripts.
  • Environment set up for testing.
  • Development of automation test harness.
  • Preparation of test suites for regression, smoke testing, and execution of similar tests in batch.


5. Test Execution and Reporting

  • Execution of test scripts either manual or automated.
  • Reporting defects found during test script execution.
  • Regression testing and retesting of fixed defects. 
  • Reporting of test execution status to stakeholders.


6.  Exit criteria

  • Evaluating Testing status against the exit criteria specified in test planning.
  • Test Status should validate that all acceptance criteria are verified.

7. Test Closure Activities

  • Delivering all the planned test artifacts to the client. For e.g : Automated Test Scripts,test scripts, test data for further reuse.
  • Handover of artifacts and knowledge transfer to maintenance team
  • Analysis of lesson learnt during testing process.

How to create a database checkpoint in QTP

A database checkpoint compares the values returned by SQL query during checkpoint execution. Below are the steps to create a database checkpoint in QTP


  • Navigate to Insert>Checkpoint>Database Checkpoint.


  • Define whether to define SQL statement manually or using Microsoft Query


  • Select the database or query if previously defined as shown below.We select QT_Flight_32 database.Click on OK.

  • Select the required columns/tables to be selected in SQL and click on next button.


  • Define conditions for selected columns in the above step and define sorting criteria. Click Next>Next


  • Click on finish



  • Change the properties of database checkpoint and select whether to insert the checkpoint before or after current step and clcik on OK. A database checkpoint is created and inserted in the test.